CASO Construction Orders ( Signal Department )

 

DATE OF ORDER

ORDER #

LOCATION

WORK DESCRIPTION

DATE COMPLETED

COST (OF SIGNAL DEPT WORK)

Feb 25/25

2819

NIAGARA RIVER

CHANGING THE EASTBOUND AUTOMATIC BLOCK SIGNALING AND INSTALLATION OF ADDITIONAL SIGNALING ACCOUNT OF NEW BRIDGE

Aug 28/26

 

Aug 11/25

2958

RIDGETOWN TO WINDSOR TOWER #4

RECONSTRUCTION OF ELECTRIC LINE BETWEEN RIDGETOWN AND WINDSOR TOWER #4

Jun 12/26

 

Sep 1/25

2934

WINDSOR

WESTBOUND CLASSIFICATION YARD - INSTALL ELECTRICAL CONNECTIONS FOR AIR BRAKE TESTING FACILITIES

Jan 4/26

$11,080.00

Sep 15/25

3009

HAGERSVILLE

REPLACE 3 WIRE CONNECTED DWARF SIGNALS WITH ELECTRIC COLOUR LIGHT SIGNALS AND SLOTTED #7 WITH TOP POST MECHANISM

Apr 25/26

 

Nov 15/25

3056

TILBURY

REPLACE GASOLINE PUMP IN PUMPING STATION WITH ELECTRICALLY DRIVEN PUMP

Sep 5/26

 

Dec 5/25

3064

WELLAND

INSTALL UNDERWATER CABLE FOR TH&B AT WELLAND DRAWBRIDGE

Jul 20/28

 

Dec 9/25

3075

WATERFORD

INSTALL ELECTRIC LIGHTS IN PUMP HOUSE AND TRACK TANK BOILER HOUSE

Apr 19/26

$180.00

Feb 3/26

3118

WELLAND

INSTALL AUTOMATIC STARTER IN PUMPING PLANT

Jun 10/26

 

Feb 6/26

3124

TILLSONBURG

CONNECT MOTOR TO OPERATE CENTRIFUGAL PUMP

Nov 4/26

 

Feb 19/26

3136

NIAGARA RIVER

INSTALL ELECTRIC LIGHTS IN 9' X 14' BUILDING AT WEST END OF NIAGARA RIVER BRIDGE

Mar 4/26

 

Mar 4/26

3157

ST. THOMAS

INSTALL TRAIN ORDER SIGNAL EAST END OF YARD AT BALL ST.

Feb 15/26

 

Mar 6/26

3162

BRIDGEBURG

WIRING CAR DEPARTMENT MACHINE SHOP & BLACKSMITH SHOP

Jun 16/26

$65.63

Apr 19/26

3208

ST.THOMAS TO RIDGETOWN

RECONSTRUCTION POLE LINE AND REPLACING ONE #10 COPPER WIRE WITH #9 COPPER WIRE

May 14/27

$7950.00

May 5/26

3236

FARGO

REPLACE WIRE-CONNECTED MECHANICALLY OPERATED SIGNALS TO PIPE CONNECTED SIGNALS CHANGING THE PRESENT SIGNALS TO TOP OF MAST MECHANISM ADDING CALLING ON SIGNAL TO WESTBOUND HOME INTERLOCKING SIGNAL AND RAISING THE LEAD-OUT TO MEET THE NEED GRADED TRACK

Oct 7/26

$7050.00

May 22/26

3259

LASALETTE

EXTENSION OF WESTBOUND ANNUNCIATOR

Jun 3/26

$125.13

May 27/26

3260

LONDON

MOVE TROLLEY POLE AND WIRE AT ENGINE HOUSE TRACK ( WORK PERFORMED BY L&PS )

Sep 2/26

$280.00

Jun 12/26

3276

MONTROSE

STOCK YARDS - REMOVE LIGHTING MATERIAL ACCOUNT OF REMOVAL OF 14 PENS IN STOCK YARD ( LEAVING 5 PENS IN USE )

Jul 15/26

 

Jun 28/26

3288

WATERFORD

ELECTRIC LIGHTING CHANGES ON WATERFORD COAL ELEVATOR

Sept 4/26

$190.55

Jul 6/26

3297

YARMOUTH

CHANGE SIGNALS 16 & 17 ON THE MCRR TO 3-POSITION UPPER QUADRANT SIGNALS AND SIGNALS 2 & 3 TO UPPER QUADRANT

Feb 12/27

$2570.00

Jul 17/26

3308

WEST LORNE

MOVE WESTBOUND TAKE SIDING SIGNAL FROM SIGNAL 1391 EAST TO SIGNAL 1381

Jul 20/26

$256.71

Jul 22/26

3316

WINDSOR

ELECTRICAL WORK ON ACCOUNT OF BUILDING 9 ADDITIONAL STALLS AND EXTENDING BOILER HOUSE AND ENGINE HOUSE

May 21/27

 

Sep 11/26

3362

WATERFORD

INSTALL 3 COLOUR LIGHT SIGNAL ON THE MAST OF THE PRESENT TRAIN ORDER SIGNAL TO REPEAT THE INDICATION OF THE EASTBOUND SIGNAL. THIS SIGNAL IS TO BE LOCATED AT A HEIGHT SO THAT IT CAN BEST BE OBSERVED BY THE ENGINEMAN OF EASTBOUND PASSENGER TRAINS WHEN THEY ARE WEST OF THE NEW COAL CHUTE.

Oct 19/26

 

Sep 30/26

3374

WATERFORD

MOVE 20 HP MOTOR ON WATER PUMP FROM PRESENT PUMP HOUSE TO NEW LOCATION NORTH OF DEPOT

Apr 25/27

$790.00

Oct 4/26

3379

ESSEX

MOVE DERAIL DWARF SIGNAL #4 AND BATTERY BOXES ACCOUNT OF EXTENSION OF ESSEX FARMERS LTD. INDUSTRIAL TRACK

Nov 9/26

 

Nov 1/26

3419

CANADA DIVISION

INSTALL LETTER "G" ON AUTOMATIC SIGNALS FOR GRADE SIGNAL INDICATION TO BE INSTALLED 6' BELOW THE LOWER ARM. LOCATIONS: EASTBOUND TRACK SIGNALS 1532, 1310, 1202 AND 1062. WESTBOUND TRACK SIGNALS 473, 493, 701 AND 1291

Dec 7/26

$10.00 each

Nov 4/26

3418

ST. THOMAS

INSTALL ELECTRIC LIGHTS AT STOCK YARDS

Nov 10/26

$195.00

Nov 10/26

3438

ST. THOMAS

INSTALL HAYES DERAIL ON THE LEAD TO THE SHOP TRACKS

Dec 23/26

$52.00

Nov 17/26

3446

DUTTON

MOVE CROSSOVER BETWEEN NORTH SIDING AND WESTBOUND MAIN 1600' EAST AND CHANGE TO A FACING POINT CROSSOVER

Nov 25/26

$1172.00

Nov 19/26

3442

TILBURY

INSTALL ELECTRIC LIGHTS IN PUMP HOUSE AND DWELLING OCCUPIED BY PUMPER

Feb 21/27

$390.00

Nov 22/26

3452

NIAGARA FALLS

INSTALL ELECTRIC LIGHTS ON NEW BRIDGE TO DETECT ALIENS FROM ENTERING US

Mar 22/27

 

Dec 10/26

3462 & 3462A

WELLAND

TEMPORARY WIRE CROSSING OVER WELLAND CANAL AT THE DRAWBRIDGE ON ACCOUNT OF MAKING EAST CHANNEL DEEPER AND DREDGING NEW WEST CHANNEL

INSTALL PERMANENT SIGNAL UNDERWATER CABLES ACROSS THE EAST & WEST CHANNEL OF WELLAND CANAL

Jun 26/29

$50550.00

Jan 5/27

3469

WINDSOR

INSTALL ELECTRIC LIGHTS OVER BENCH VISES IN WINDSOR ROUNDHOUSE

Mar 5/27

$250.00

Jan 28/27

3485

NIAGARA FALLS

INSTALL ELECTRIC LIGHTS IN WATCHMAN'S HOUSE - EAST END OF NIAGARA RIVER BRIDGE

Jan 11/27

 

Mar 21/27

3518

WINDSOR

INSTALL ELECTRIC LIGHTS IN TELEPHONE BOOTHS IN WINDSOR STATION

CANCELLED MAR 26/27

 

Apr 28/27

3565

SOUTHWOLD

RETIREMENT OF TRAIN ORDER SIGNALS

May 10/27

-$204.00

Apr 28/27

3566

NIAGARA-ON-THE-LAKE

RETIREMENT OF TRAIN ORDER SIGNALS

May 15/27

-$204.00

May 4/27

3570

VICTORIA PARK

DIVERSION OF MAIN TRACK - ACCOUNT PROPOSED NEW SUBWAY

Oct 27

 

May 5/27

3573

ST. THOMAS

ELECTRICAL CONNECTIONS FOR OXWELD RAILROAD SERVICE. OXWELD HAS CONSTRUCTED AT ITS EXPENSE AND ACETYLENE GENERATOR BUILDING AND PLANT AND REQUIRES CONNECTIONS TO THE GENERATOR BUILDING FOR ELECTRIC SERVICE

Apr 6/27

$25.00

May 18/27

3583

TAYLOR

CONNECTING UP OF THE AUTOMATIC BLOCK SIGNAL FOR SWITCH LEADING ON TO THE EAST END OF THE NORTH PASSING TRACK

May 13/27

 

Jun 14/27

3598

LEAMINGTON

INSTALLATION OF SWITCH CONNECTED DERAIL ON IMPERIAL TOBACCO TRACK.

Jul 7/27

 

Jul 8/27

3620

WINDSOR

INSTALL ELECTRICAL CONNECTIONS FOR COAL UNLOADER AND MOTOR DRIVEN PUMP. COAL UNLOADER FROM WEST DETROIT LOCOMOTIVE SHOPS BOILER ROOM

Nov 15/27

 

Aug 11/27

3648

WINDSOR

INSTALL LIGHTING FOR NEW 100' TURNTABLE REPLACING 85' TURNTABLE

Nov 15/27

 

Sep 2/27

3665

STEVENSVILLE

INSTALLATION OF TWO WIGWAG SIGNALS IN ADDITION TO PRESENT BELL AT VICTORIA AVE.

Oct 26/27

$749.20

Sep 19/27

3677

ST. THOMAS

INSTALLATION OF 3 POSITION COLOUR LIGHT SIGNAL EAST OF THE DEPOT TO REPLACE THE PRESENT AUTOMATIC BLOCK SIGNAL ON BRACKET MAST

Dec 30/27

$917.10

Sep 21/27

3686

WINDSOR

INSTALL ELECTRIC LIGHTS IN NEW BUILDING TO BE USED FOR STORING ARCH BRICK

Nov 28/27

 

Nov 8/27

3741

CORNELL

CONNECTING WITH THE AUTOMATIC BLOCK SIGNALING A TEMPORARY SWITCH LOCATED IN THE EASTBOUND MAIN TRACK NEAR MP 85. TEMPORARY TRACK IS TO BE USED IN CONNECTION WITH THE REBUILDING OF OTTER CREEK BRIDGE.

Jul 7/28

 

Nov 10/27

3748

WINDSOR

MOVING POLE LINE TO MAKE ROOM FOR CINDER TRACK

Nov 25/27

 

Nov 17/27

3752

SHEDDEN

REMOVAL OF CROSSOVER BETWEEN THE EXTENSION TO THE SPUR TRACK AND EASTBOUND MAIN. DURING 1926 THE SPUR TRACK WAS EXTENDED 960' AND THE CROSSOVER BETWEEN THE EASTBOUND MAIN AND THE SPUR TRACK INSTALLED FOR THE PURPOSE OF UNLOADING ROAD BUILDING MATERIAL FOR THE DUFFERIN CONSTRUCTION. ON MAY 14, 1927 - THE CROSSOVER WAS REMOVED AND THE SPUR EXTENSION WILL REMAIN.

Nov 14/27

 

Nov 23/27

3757

CANFIELD JUNCTION

INSTALLATION OF WIGWAG WITH CROSSING BELLS ONE ON EACH SIDE OF TRACK AT SIDE OF STREET - CROSSING 3 MILES EAST OF CANFIELD JUNCTION

Dec 22/27

$966.00

Dec 14/27

3774

SHEDDEN

RETIREMENT OF TRAIN ORDER SIGNAL

Dec 23/27

-$204.00

Dec 16/27

3777

BROOKFIELD

INSTALLATION OF WIGWAG SIGNALS AND BELLS - NEIDLES ROAD, BROOKFIELD

Feb 5/28

$2969.08

Jan 23/28

3787

NIAGARA FALLS TO FRASER

INSTALL COLOUR LIGHT SIGNALS - GENERAL RAILWAY SIGNAL CO. TYPE S TO REPLACE EXISTING SEMAPHORE SIGNALS - DISTANCE 5 MILES

May 4/29

$9815.78

Feb 2/28

3791

LASALETTE

INSTALLATION OF ELECTRIC LIGHTS

May 5/28

$96.30

Feb 20/28

3800

WATERFORD

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS - ST. JAMES ST. WATERFORD

May 8/28

$2850.26

Feb 29/28

3801

WINDSOR

INSTALLATION OF INDUCTORS FOR TESTING TRAIN CONTROL EQUIPMENT ON ENGINES

Mar 1/28

$110.00

Feb 29/28

3802

ST. THOMAS

INSTALLATION OF INDUCTORS FOR TESTING TRAIN CONTROL EQUIPMENT ON ENGINES

Apr 25/28

$160.00

Mar 5/28

3810

LONDON

MOVING TROLLEY WIRE AND POLE - PASSENGER STATION AT LONDON HAS BEEN LEASED TO LAINGFORD & EDWARDS. MCR WILL MOVE TRACKS NEAR STATION

May 5/28

$486.00

Apr 9/28

3821

NIAGARA FALLS TO MONTROSE

RECONSTRUCT T&T POLE LINE FOR WESTERN UNION - REPLACE DAMAGED CROSSARM PINS AND INSULATORS

May 23/29

$750.00

Apr 16/28

3828

VICTORIA

INSTALLATION OF FLOODLIGHTS IN THE EASTBOUND CLASSIFICATION YARD AT VICTORIA WHICH IS WEST OF THOMPSON ROAD AND IS THE OLD TH&B YARD

Aug 27/28

$1040.00

Apr 16/28

X-796

NIAGARA-ON-THE-LAKE

RETIREMENT OF STATION

 

 

Apr 27/28

3837

HAGERSVILLE

CHANGE THE LOCATION OF EASTBOUND AUTOMATIC BLOCK SIGNALS #514 AND #542

Jun 21/28

$435.00

May 8/28

3846

SPRINGFIELD

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS - EAST ST. SPRINGFIELD - ALSO UPGRADE CIRCUIT FOR CROSSING BELLS AT HORNSBY ROAD

May 31/28

$685.44

Jul 7/28

3892

WOODSLEE

INSTALLATION OF HIGHWAY CROSSING BELLS & WIGWAG SIGNALS. MAIN ST. WOODSLEE

Jul 25/28

$748.06

Jul 8/28

3896

MONTROSE

INSTALLATION OF INDUCTORS FOR TESTING TRAIN CONTROL EQUIPMENT ON ENGINES

Oct 2/28

$150.00

Jul 9/28

3883

WEST LORNE

INSTALL WIRING FOR ELECTRICALLY OPERATED CENTRIFUGAL PUMP AT WEST LORNE PUMPING STATION

Jul 17/29

 

Jul 11/28

3897

VICTORIA

INSTALLATION OF INDUCTORS FOR TESTING TRAIN CONTROL EQUIPMENT ON ENGINES

Oct 1/28

$50.00

Jul 23/28

3915

HAGERSVILLE

INSTALLATION OF WESTBOUND PASSING TRACK - 1 MILE WEST OF HAGERSVILLE. WESTBOUND AUTOMATIC HOME BLOCK SIGNAL #563 TO BE MOVED EAST OF THE EAST SWITCH

Aug 22/28

$1583.88

Jul 24/28

3914

FORKS CREEK

INSTALLATION OF POWER AND LIGHTS FOR PUMPING STATION

Jan 11/29

$1250.00

Jul 25/28

3911

WINDSOR

INSTALL 500 WATT ANGLE REFLECTOR ON THE EASTBOUND HUMP AND WESTBOUND HUMP

Sep 20/28

$200.00

Jul 25/28

3919

LEAMINGTON

INSTALLATION OF SWITCH CONNECTED DERAIL. 2 NEW TRACKS TO BE INSTALLED - THE SWITCH OF THE SECOND TRACK IS LOCATED NEAR THE FOULING POINT FROM THE MAIN TRACK SO THAT THE SWITCH CONNECTED DERAIL CAN BE INSTALLED JUST AHEAD OF THIS SECOND SWITCH

Aug 14/28

 

Aug 3/28

3930

AMHERSTBURG

INSTALLATION OF SWITCH CONNECTED DERAIL AT BOARDER BREWERS & DISTILLERS INDUSTRIAL TRACK THE SWITCH TO BE LOCATED 400' NORTH OF THE CROSSING OF THE HYDRO-ELECTRIC COMPANY.

Aug 25/28

 

Aug 7/28

3932-A

TILBURY

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT PROVINCIAL HIGHWAY #2 -2.5 MILES EAST OF TILBURY

Nov 24/28

$2490.57

Aug 7/28

3933-A

TILLSONBURG

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT BROADWAY ST. .94 MILES WEST OF TILLSONBURG

Nov 24/28

$2124.48

Aug 7/28

3935

MONTROSE

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT STONE RD - .13 MILES SOUTH OF MONTROSE JCT.

Dec 3/28

$1421.02

Aug 8/28

3936

BRIDGEBURG

INSTALLATION OF SWITCH CONNECTED DETAIL ON HORTON STEEL INDUSTRIAL SWITCH

Sep 14/28

 

Aug 8/28

3941-A

PERRY

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT WILFORD ROAD - 2.6 MILES EAST OF PERRY

Nov 7/28

$1694.60

Aug 8/28

3942-A

CANFIELD

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT TALBOT ROAD - 1.9 MILES WEST OF CANFIELD

Dec 10/28

$1605.94

Aug 8/28

3943-A

RUSCOMB

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT MIDDLE ROAD - RUSCOMB

Aug 27/28

$2153.88

Aug 10/28

3944-A

TOWNSEND CENTRE

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT TOWNSEND CENTRE

Dec 15/28

$2928.50

Aug 11/28

3945-A

BROWNSVILLE

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT CROSSING NEXT TO STATION - BROWNSVILLE

Dec 31/28

$2211.35

Aug 11/28

3946-A

YARMOUTH

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT BELMONT RD - 1.6 MILES EAST OF YARMOUTH

Jan 24/29

$1031.36

Aug 16/28

3951

HAGERSVILLE

INSTALL SWITCH CONNECTED HAYES DERAIL AT THE EAST END OF THE SOUTH PASSING TRACK

Sep 18/25

$285.00

Sep 6/28

3979

WINDSOR

INSTALL HALF INTERLOCKING PLANT - CROSSING OF THE MCRR SINGLE TRACK LEADING TO THE DOCK AND ELECTRIC RAILWAY COMPANYS TRACKS - FIELD AVE - WINDSOR

Oct 19/28

 

Oct 1/28

4002

ST. THOMAS

INSTALL WIGWAG SIGNALS IN ADDITION TO CURRENT BELL - PRINCESS ST. - ST. THOMAS

Dec 6/28

$840.44

Oct 10/28

4005

TILBURY

INSTALL SWITCH-CONNECTED DERAIL AND CONNECT WITH AUTOMATIC BLOCK SIGNALS - NEW INDUSTRIAL SWITCH OFF EASTBOUND MAIN FOR THE CANADIAN TOP & BODY CORP. - TILBURY

Nov 15/28

 

Oct 10/28

4014

TILBURY

INSTALL DERAIL AND CONNECT WITH AUTOMATIC BLOCK SIGNALS - NEW INDUSTRIAL SWITCH OFF WESTBOUND MAIN FOR THE CANADIAN TOP & BODY CORP. - TILBURY

Nov 8/28

 

Nov 1/28

4042

ST. THOMAS

INSTALL FOUR 60 WATT LAMPS IN SAND HOUSE NEAR COAL ELEVATOR

Oct 30/28

 

Nov 28/28

4083

NIAGARA FALLS

INSTALL SWITCH CONNECTED DERAIL FOR NEW INDUSTRIAL TRACK TO SERVE PENINSULAR DISTILLING CO.

Dec 11/28

 

Dec 3/28

4077

ST. THOMAS

MOVE CROSSOVER FROM #1 TRACK ST.THOMAS YARD TO EASTBOUND MAIN TRACK 100' EAST

Nov 2/28

 

Dec 4/28

4085

VICTORIA

ELECTRICAL CONNECTIONS FOR NEW 100' TURNTABLE AT VICTORIA ROUNDHOUSE

Dec 11/28

 

Dec 5/28

4044

PERRY

NORTH SIDING AT PERRY IS TO BE EXTENDED 1900' EAST

Nov 3/28

 

Dec 5/28

4086

PERRY

SOUTH SIDING AT PERRY IS TO BE EXTENDED 1900' EAST

Nov 1/28

 

Dec 5/28

4087

TILBURY

NORTH SIDING AT TILBURY IS TO BE EXTENDED 1300' EAST

Nov 13/28

 

Dec 5/28

4088

WATERFORD

SOUTH SIDING AT WATERFORD IS TO BE EXTENDED 2200' WEST

Nov 10/28

 

Dec 5/28

4089

WELLAND

NORTH SIDING AT WELLAND TO BE EXTENDED 1900' WEST

Nov 1/28

 

Dec 6/28

4045

TILLSONBURG

SOUTH SIDING AT TILLSONBURG IS TO BE EXTENDED 1500' EAST

Nov 6/28

 

Dec 6/28

4054

TILLSONBURG

NORTH SIDING AT TILLSONBURG IS TO BE EXTENDED 2400' EAST

Nov 30/28

 

Dec 28/28

4104

WELLAND

INSTALLATION OF 2 35' POLES AND 200 WATT LAMPS ON PLATFORM EXTENSION

Jan 4/29

$200.00

Jan 10/29

4130

TILBURY

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT TILBURY ST - TILBURY

 

$1875.00

Jan 10/29

4131

TILBURY

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT QUEEN ST - TILBURY

 

$1591.20

Jan 10/29

4132-A

TAYLOR

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT BLAKES RD - 1.11 MILES EAST OF TAYLOR

 

$1604.92

Jan 10/29

4133-A

CHARING CROSS

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT WHITES CROSSING - CHARING CROSS

Aug 22/29

$1637.63

Jan 10/29

4134-A

TAYLOR

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT TOWN LINE RD - .5 MILES WEST OF TAYLOR

Apr 10/29

$2126.87

Jan 10/29

4135-A

HIGHGATE

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT TOWN LINE RD - 2.42 MILES WEST OF HIGHGATE

Apr 23/29

$1946.42

Jan 10/29

4136-A

FARGO

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT COMMUNICATION ROAD - .89 MILES EAST OF FARGO

Apr 30/29

$1974.68

Jan 10/29

4137-A

WEST LORNE

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT CONCESSION RD - .75 MILES EAST OF WEST LORNE

 

$2032.00

Jan 10/29

4138-A

VILLA NOVA

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT E.QUARTER LINE ROAD EAT OF STATION - VILLA NOVA

Feb 27/29

$1927.81

Jan 10/29

4139-A

DUFFERIN

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT DUFFERIN ROAD - WEST OF STATION AT DUFFERIN

Aug 20/29

$1842.82

Jan 10/29

4140-A

WELLAND

INSTALLATION OF HIGHWAY CROSSING WIGWAG SIGNALS AND BELLS AT PROVINCIAL HIGHWAY - 2.73 MILES EAST OF WELLAND

Feb 5/29

$1651.83

Feb 19/29

4157

MONTROSE

REMOVAL OF ELECTRIC FACILITIES AT MONTROSE ICE PLATFORM ( TO BE REMOVED)

 

 

Mar 1/29

4159

HAGERSVILLE

INSTALL WIGWAG SIGNALS AND BELLS - TUSCORORA ST. - HAGERSVILLE

Mar 15/29

$1971.04

Mar 1/29

4160

ST. THOMAS

INSTALL NINE 500 WATT INDIRECT LIGHTING FIXTURES TO REPLACE 24 60 WATT DROP LIGHTS IN APPRENTICE SCHOOL ROOM

Apr 12/29

$375.00

Mar 7/29

4161

ST. THOMAS

INSTALL ELECTRIC LIGHTS AT ST. THOMAS STORE HOUSE FOR CANADA CUSTOMS

Feb 21/29

 

Mar 8/29

4165

TOWNSEND CENTRE

INSTALL WIGWAG SIGNALS IN ADDITION TO CURRENT BELL - 9TH CONCESSION ROAD - TOWNSEND CENTRE

Mar 6/29

 

Mar 16/29

4170

ST. THOMAS

INSTALL WIGWAG SIGNALS IN ADDITION TO CURRENT BELL - HINKS ST. - ST. THOMAS

Mar 20/29

 

Apr 8/29

4188

BLACK CREEK

REMOVE TRAIN ORDER SIGNAL - AGENCY STATION CLOSED IN 1927 - STATION RECENTLY REMOVED

May 17/29

$50.00

Apr 8/29

4190

WEST LORNE

EASTBOUND PASSING SIDING AT WEST LORNE IS TO BE EXTENDED 1658' WEST

May 15/29

$165.57

Apr 8/29

4191

WEST LORNE

WESTBOUND PASSING SIDING AT WEST LORNE IS TO BE EXTENDED 2134' EAST - SIGNAL #1391 IS TO BE MOVED 1450' EAST

Apr 4/29

$1146.24

Apr 8/29

4192

TILBURY

EASTBOUND PASSING SIDING AT TILBURY IS TO BE EXTENDED 973' EAST

Sep 10/29

$494.40

Apr 8/29

4193

LASALETTE

EASTBOUND PASSING SIDING AT LASALETTE IS TO BE EXTENDED 2190' EAST

May 2/29

$290.00

Apr 30/29

4212

ST. THOMAS

SIGNAL WORK IN CONNECTION WITH TEMPORARY TRACKS FOR THE RECONSTRUCTION OF KETTLE CREEK VIADUCT

Aug 14/30

 

May 16/29

4223

NIAGARA FALLS

INSTALLATION OF LIGHTNING FLASHLIGHT SIGNALS AT SIMCOE ST. & ONTARIO AVE. - NIAGARA FALLS

Jul 31/29

$2175.90

May 16/29

4224

NIAGARA FALLS

INSTALLATION OF LIGHTNING FLASHLIGHT SIGNALS AT EASTWOOD AVE. - NIAGARA FALLS

Jul 31/29

$2140.32

May 16/29

4225

NIAGARA FALLS

INSTALLATION OF LIGHTNING FLASHLIGHT SIGNALS AT CLIFTON HILL STREET - NIAGARA FALLS

Jul 29/29

$1752.16

May 16/29

4226

NIAGARA FALLS

INSTALLATION OF LIGHTNING FLASHLIGHT SIGNALS AT MORRISON STREET - NIAGARA FALLS

Jul 31/29

$1581.08

May 16/29

4227

NIAGARA FALLS

INSTALLATION OF LIGHTNING FLASHLIGHT SIGNALS AT HURON & ERIE STREETS - NIAGARA FALLS

Jul 31/29

$2282.33

May 21/29

4230-A

MONTROSE

INSTALLATION OF MORRISON LIGHTNING FLASHLIGHT SIGNALS AT STANLEY ST. - MONTROSE

Jul 30/29

$1535.98

May 21/29

4231-A

FRASER

<